Solar DAS and SCADA Defined

REIG Solar Technical Team
Solar DAS and SCADA Defined

This is the first post in a series on the technical side of solar PV monitoring and control. Before going further, it helps to define DAS and SCADA clearly, since installers, asset owners, and utility reviewers often use the two terms as if they were interchangeable, even though they describe two different levels of capability. A Data Acquisition System reports what a solar plant is doing. A Supervisory Control and Data Acquisition system does that, and lets an operator act on it.

What Do DAS and SCADA Mean in Solar PV?

DAS is an acronym for Data Acquisition System. That is nothing more than a term for a system with the ability to poll or query field-installed devices, which carry information inside their own operating systems, and then collect that data into a table, spreadsheet, or database for someone to review. It is a reporting layer, nothing more.

SCADA, on the other hand, is more complex and provides more functionality. SCADA stands for Supervisory Control And Data Acquisition. Note that data acquisition is part of that name and performs the same job a DAS performs. But a SCADA system also uses that data to supervise and control equipment, not just report on it.

Two examples from the field help make the DAS and SCADA distinction concrete: a small, simple solar farm that only needs to be watched, and a much larger one that a utility requires to be controlled.

A Basic DAS System: Old MacDonald's 1 MW Solar Farm

Old MacDonald had a farm, a solar farm, and it was a small one: about 1 MW of AC delivery capacity. It was a fixed-tilt racking system, with two 500 kW central inverters, a site meter, and a basic weather station. All Farmer MacDonald wanted was information from the system: how it was performing, what the irradiance and temperatures were, and some notice if something was not functioning quite right. His provider suggested a basic DAS with the ability to log in to a web-based monitoring dashboard that showed everything the farmer needed to know. No control functions, no utility mandate, just clean reporting.

Scaling Up: Mac Jr.'s 60 MW SCADA System

Old MacDonald's son, Mac Jr., had bigger plans. He had about 200 acres under cultivation, of a cash crop called solar PV. In total, about 60 MW AC capacity, with 20 inverter and transformer skids, single-axis tracker racking, more weather sensors than you could count, and the best thing of all, his own personal substation connected to the transmission grid at 115 kV.

That boy was proud of that farm, but getting it connected to the grid took a lot of work to meet the utility's requirements for remote control, grid support for frequency and voltage regulation, reactive power support, and the ability to throttle the plant back, or turn it off completely, when needed. Interconnection terms like these are typically built around IEEE 1547, the industry standard for interconnecting distributed energy resources with the grid, and are enforced through the reliability framework maintained by NERC.

Mac's EPC was sharp too, and provided an industrial-grade communications infrastructure out in the field to connect everything together, then installed and programmed a rack full of computers, RTACs, managed Ethernet switches, and fiber optic cable throughout the substation. One of those computers runs the SCADA software that keeps everything communicating, reporting, and saving the data acquired from the arrays, while letting the utility control and regulate the site to meet its requirements. The rest of the equipment keeps the plant connected to the grid and makes the physical connections to field devices such as inverters, tracking controllers, and weather instruments. Readers who want the underlying resource data behind irradiance and weather monitoring can start with NREL's solar resource and monitoring data.

And just like Old MacDonald, Mac Jr. had a web-based display that showed everything happening on the site, and whether it was working as expected. Same kind of information his father had, but a great deal more of it, and those dashboard buttons could turn equipment on or off when needed too. His father's system was never that capable, because it never needed to be.

Key Differences Between DAS and SCADA for Solar PV

The table below summarizes how DAS and SCADA diverge once a project scales from a simple rooftop or small ground-mount array up to a utility-interconnected plant.

CapabilityDAS (Data Acquisition System)SCADA (Supervisory Control and Data Acquisition)
Primary functionCollects and reports performance dataCollects data and issues control commands
Typical plant sizeUnder roughly 5 MW AC, inverter-meteredUtility-scale, often 20 MW AC and above
Interconnection voltageDistribution levelOften transmission level, such as 115 kV
Utility control requirementNoneCurtailment, voltage/VAR support, remote disconnect
Core hardwareGateway/logger, site meter, weather stationRTAC, managed switches, fiber network, substation computers

This is a basic comparison, and there is more to learn about becoming a solar data expert. We will cover the hardware that makes each system work, and how the data is collected, stored, and reported, in future posts in this series. In the meantime, our SCADA integration services page walks through how REIG scopes a control system for a given interconnection agreement, and our monitoring series hub indexes every post as it publishes.

Why Utility-Scale Solar Needs DAS and SCADA Working Together

No utility-interconnected plant above a few megawatts gets to skip this step. The interconnection agreement, not the plant owner's preference, decides whether DAS alone is enough or whether full SCADA is required. Projects that anticipate growing past their initial size, or adding a future substation, do better to design the communications backbone for SCADA from day one rather than retrofitting it later. For background on how reactive power and voltage ride-through obligations get set at the federal level, see the FERC electric transmission interconnection resources, and for a plain-language industry overview of utility-scale solar deployment trends, the SEIA research library is a solid starting point. If your project's interconnection terms are still being negotiated, our team can help you map which obligations will require DAS and SCADA together before the agreement is signed; see our interconnection support page for details.

Basic DAS data flow: field devices to dashboard, one-way reporting only Inverters DAS Logger Web Dashboard SCADA data flow: field devices to RTAC and operator, with a return control path Inverters/Trackers RTAC/SCADA Operator/Utility Control / curtailment commands return to the field

We cover the details separately in OPC UA for Utility-Scale Solar SCADA: IEC 62541 Integration Guide.

Frequently Asked Questions About Solar Monitoring and Control

What is the difference between DAS and SCADA in solar power plants?

A Data Acquisition System (DAS) polls inverters, meters, and weather instruments, then stores that data for reporting, typically through a web dashboard showing irradiance, output, and alarms. A Supervisory Control and Data Acquisition (SCADA) system starts from that same data layer but adds the ability to act on it: issuing setpoints to inverters, curtailing output, or adjusting reactive power in response to a utility request. In short, DAS and SCADA both collect data, but only SCADA closes the loop with remote control. Most small, inverter-metered solar farms only need DAS; larger plants connected at transmission voltage almost always need SCADA.

Do I need a SCADA system for a small solar farm?

Usually not. A small, fixed-tilt farm in the 1 MW AC range with one or two central inverters and a site meter typically has no utility requirement to accept remote control commands, so a basic DAS with web-based reporting covers the need: performance tracking, irradiance and temperature logging, and fault alerts. SCADA becomes necessary once a project interconnects at a higher voltage, such as a dedicated substation tied to the transmission grid, because the utility will require frequency and voltage support, reactive power control, and the ability to curtail or disconnect the plant remotely. Plant size alone does not decide this; the interconnection agreement does.

What utility requirements make SCADA mandatory for solar interconnection?

Utilities typically require SCADA when a solar plant interconnects at transmission-level voltage or contributes enough capacity to affect grid stability. Common requirements include remote curtailment, ride-through and voltage regulation behavior aligned with IEEE 1547, reactive power (volt/VAR) support, and the ability for the utility or transmission operator to disconnect the plant on demand. These obligations are spelled out in the interconnection agreement negotiated with the utility and, for larger projects, reviewed against regional transmission organization and NERC reliability standards. A DAS alone cannot satisfy these obligations because it has no control path back into the plant.

What hardware is inside a solar SCADA system?

A utility-scale solar SCADA system typically runs on a rack of industrial computers and remote terminal units (RTACs) housed in the project substation, connected to managed Ethernet switches and fiber optic cabling that reach every inverter skid, tracker controller, and weather station in the field. The SCADA software on those computers polls each device, logs the data, displays it on an operator dashboard, and sends control commands back out when the utility requests a change in output, voltage, or reactive power. The communications network itself, not just the software, is what makes DAS and SCADA reliable at a 60 MW scale with twenty or more inverter skids.

Can a DAS system be upgraded to SCADA later?

In many cases, yes, provided the underlying communications infrastructure supports it. Because DAS and SCADA share the same data acquisition foundation, a DAS deployment built on industrial-grade networking, such as managed switches and fiber rather than consumer-grade equipment, can often be extended with an RTAC and control software to add supervisory functions later. Projects that start small and expect to add capacity, additional inverter skids, or a future substation interconnection should plan the original DAS wiring and network architecture with that upgrade path in mind, since retrofitting communications infrastructure after the fact costs far more than specifying it correctly the first time.

Thanks for stopping by, and I hope to see you all again soon.

Keith

###

Keith Davis is the president of Renewable Energy Integration Group (REIG), a Charlotte, NC based firm focused on all things control, data acquisition, and SCADA in the commercial, industrial, and utility solar PV marketplace. He and his team are leaders in the industry and provide professional hardware, dependable monitoring software, and service beyond the expected. We take the complexity out of solar data.